Jonesboro Road Interchange Improvements

Fast Facts

Project # I-5883
Type: Interchange improvements
Affected Counties: Harnett
Estimated Cost: $15,080,000

Description

The N.C. Department of Transportation (NCDOT) proposes improvements at Exit 75 at I-95/Jonesboro Road (SR 1808), and Exit 77 at I-95/Hodges Chapel Road (SR 1709).

These improvements are part of the broader I-95 and US 70 updates. The purpose of the construction is to improve safety, traffic flow, and repair the quality of the roads. Interchanges between Exit 70 and Exit 77 were built in the 1960s and are outdated and need to be brought into compliance with today’s safety standards to accommodate an eventual eight-lane I-95.

Improvements will have longer on and off ramps, and taller, longer overpasses big enough to cross I-95 when this stretch is widened to eight lanes in 2026.

While many residents anticipated this construction, some have expressed concerns about the impact these changes could have on the community, including homes and businesses.

News/Publications

Maps

Project Schedule

  • Right-of-way acquisition - 2018
  • Start Construction - 2019
  • End Construction - 2021

Property Takings

It is estimated that more than 50 parcels of property will be impacted by this project. Currently the NCDOT has set aside $1,080,000 for right-of-way takings. If your property will be affected, contact one of our attorneys (two of whom previously worked on behalf of the NCDOT) for a free case evaluation.