US 19/74/64/129 Improvements

Fast Facts

NCDOT TIP # R-5735
Project Type:
 Improve Roadway
Affected Counties:
 Cherokee
Estimated Cost: $
 14,078,000

Description

The North Carolina Department of Transportation (NCDOT) plans to improve a 1.25-mile section of U.S. 19/74/64/129 from about three-quarters of a mile southwest of Murphy to Hiwassee Street near the First Baptist Church.

Improvements could involve increasing lane widths, adding turn lanes, raised medians, and removing driveways. More than 35 property owners will be affected by these changes.

The NCDOT asserts that these improvements will address traffic congestion and improve the overall safety and traffic flow.

Map

Schedule

  • Right-of-way acquisition - 2018
  • Start Construction - 2019
  • End Construction - 2020

Property Takings

It is estimated that more than 35 parcels of property will be impacted by this project. Currently the NCDOT has set aside $1,460,000 for right-of-way takings. If your property will be affected, contact one of our attorneys (two of whom previously worked on behalf of the NCDOT) for a free case evaluation.

locations