NC-211 Widening (Holly Grove School Road to NC-73)

Fast Facts

Project #R - 5726
Type: Road Widening
Affected Counties: Moore
Estimated Cost: $44,233,000


The North Carolina Department of Transportation (NCDOT) plans to widen to four lanes a 7.1-mile stretch of NC-211 from NC-73 to Holly Grove School Road (SR 1241) in West End, North Carolina.

The purpose is to create a continuous four-lane boulevard stretching through Moore County – from Hoke County to east Montgomery County.


The Pilot: Public Meeting on Road Widening Plans in West End

Proposed Plan Alternative

Project Schedule

  • Right-of-way acquisition - 2018
  • Start Construction - 2020
  • End Construction - 2024 

Property Takings

It is estimated that more than 40 parcels of property will be impacted by this project. Currently the NCDOT has set aside $14,233,000 for right-of-way takings. If your property will be affected, contact one of our attorneys (two of whom previously worked on behalf of the NCDOT) for a free case evaluation.